Gathering Information

Phase 1A

Establishing a Preliminary Understanding of the I-40 Prewitt Interchange.

Phase 1A precedes detailed analysis and alternative screening in Phase 1B. This initial phase establishes baseline conditions crucial for future design decisions.

I-40 Prewitt Guardrail.png

Safety Conditions

Summer of 2024, our study team began Phase 1A of the I-40 Prewitt Interchange reconstruction project, focusing on existing conditions analysis and initial alternatives development. 

 

The phase includes studying current safety concerns at Exit 63, including damaged guardrails and insufficient turn radius for commercial vehicles at the westbound off-ramp onto Route 66/ NM 122. 

Semi Truck Turning at Exit 63_edited.png

Damaged Guardrail at I-40 Exit 63

Semi-Truck Turning at I-40 Exit 63

Road Conditions

​Additional existing road conditions that were noted by the study team include:​​​

​

The existing road over I-40, Pillowcrest Road, will limit future I-40 improvements identified and recommended by the 2024 NMDOT I-40 Corridor Study. 

​

Insufficient lane lengths for safe acceleration and deceleration for on/off ramps. 

​

​

Area Map of I-40 Prewitt Interchange.png

Public Involvement

On Oct. 9, 2024, the first public meeting was held to inform the community of the upcoming study. A public comment period was held through Nov. 9, 2024, gather community input on driver experience within the study area. Feedback gathered will help the study team understand how the existing interchange serves you and where improvements are needed most. To view materials from the public meeting, click on the button below. 

For more information in another language, please reach out to our study team at the email address provided.​